12/01/2021
2021: the Alba synchrotron begins its mutation
2021: the Alba synchrotron begins its mutation
"10 years illuminating the unknown" is the current motto of the synchrotron (see image). And for many more years to come, since in December last year the ALBA Synchrotron Board gave the green light to start working on the ALBA II project in 2021, which will transform ALBA into a 4th generation synchrotron.
The 4th generation synchrotrons, compared to the 3rd generation ones, produce a much brighter beam of light with better coherence properties, providing matter analysis capabilities that are now inaccessible in terms of resolution, detection level and understanding of matter properties.
The ALBA II project envisages the transformation of the ALBA Synchrotron from 3rd to 4th generation through the partial replacement of its accelerator, the construction of new experimental beam lines and the upgrading of some components of the existing beam lines.
The design and construction of the ALBA II project will be carried out between 2021 and 2028, maintaining the current operation of the ALBA synchrotron. A technical shutdown is planned between 2029 and 2030 to install and test the new components, and research activity will resume in 2031.
Since its inauguration in 2010, the ALBA synchrotron has consolidated itself as an exceptional tool for science with more than 1,500 experiments published in over 1,300 articles in specialized magazines. The ALBA II project represents a leap forward that will allow this infrastructure to continue at the forefront of science, technology and innovation.
The 4th generation synchrotrons, compared to the 3rd generation ones, produce a much brighter beam of light with better coherence properties, providing matter analysis capabilities that are now inaccessible in terms of resolution, detection level and understanding of matter properties.
The ALBA II project envisages the transformation of the ALBA Synchrotron from 3rd to 4th generation through the partial replacement of its accelerator, the construction of new experimental beam lines and the upgrading of some components of the existing beam lines.
The design and construction of the ALBA II project will be carried out between 2021 and 2028, maintaining the current operation of the ALBA synchrotron. A technical shutdown is planned between 2029 and 2030 to install and test the new components, and research activity will resume in 2031.
Since its inauguration in 2010, the ALBA synchrotron has consolidated itself as an exceptional tool for science with more than 1,500 experiments published in over 1,300 articles in specialized magazines. The ALBA II project represents a leap forward that will allow this infrastructure to continue at the forefront of science, technology and innovation.
More news
27/06/2017
Barcelona Synchrotron Park’s sustainable brownfield restoration program presented at AquaConSoil 2017
21/06/2017
Catalonia confirms itself as pole of attraction for foreign investments
15/06/2017
Construction of the Natura Bissé’s new world headquarters is well on its way
06/06/2017
Walk in the Park: the biodiversity routes await you
31/05/2017
UAB second most innovative university in Spain
24/05/2017
PRUAB: 10 years in strengthening relationships between research and business fabric